An honorary sequel to Power 2026November 2026

capacity2026

The complete primer on data-center capacity procurement. Sixteen chapters on what capacity physically is, how America administers it, how data centers buy it, and what comes next.

By Ben Hilborn · Elastic Energy

Learn this your own way with

One line, one day Illustrative 24-hour chart. The static rating is flat at 100 percent. The weather-adjusted rating sits above it most of the day, peaking near 145 percent before dawn and dipping to about 105 percent in late afternoon. The gap between them is labelled hidden capacity. 80%100%125%150%00:0006:0012:0018:0024:00 hidden capacity static rating (worst case) what the wire can carry, hour by hour binding hour
Fig. 0 The node question, illustrated. A line rated for the worst hour carries spare capability in the other twenty-three. Illustrative shape, not a measured line.
Preface

If you haven't read Neel Somani's Power 2026, start there. It is the clearest on-ramp I know to how electricity gets its price: the merit order, the marginal generator, the production cost model, and the moment a transmission line maxes out so the price on one side walks away from the price on the other. Somani closes on "it depends," followed by: "But now you're equipped to answer."

Power 2026 gives capacity markets a passing mention. This primer picks up there and trades one unit for another.

Power 2026 is mostly about the megawatt-hour: energy, priced in dollars per MWh, set by whichever generator sits on the margin in a given five-minute interval. Every data center developer eventually learns that a second number on the utility engineering study decides whether the building gets energized at all. That unit is the megawatt: how much power the network can guarantee it will deliver to a specific bus, during the specific hours when the local grid is stressed. We call that capacity, and remarkably few institutions can tell you what it actually is in real time.

I'm an electrical engineer by training and a co-founder of Elastic Energy, where we build hardware and software that makes distributed energy resources visible and dispatchable. Most of my working hours are spent at the grid edge, downstream of the substation breaker, where utility SCADA visibility drops off and physical headroom goes unmeasured. I wrote this for the same audience Power 2026 reached: founders, infrastructure investors, utility engineers, and anyone trying to understand the physical bottleneck governing the AI buildout.

Sixteen chapters, four parts, one argument: capacity begins as a nodal, hourly physical limit. Every capacity market in America is a lossy compression of that limit. And the fastest way to connect new load is to instrument, verify, and transact the physical headroom our static planning rules leave unused.

Fact-checked against primary regulatory filings, ISO auction reports, and court dockets through November 2026.

Part 1 / 4

Capacity is a physical fact first

Everyone in the AI infrastructure world agrees that power capacity is the bottleneck. Data center load requests are arriving faster than transmission planners can study them, interconnection queues stretch past the end of the decade, and utilities are rationing service agreements across major load pockets.

Yet ask the simplest physical question in the debate (at 6:00 PM on a hot August Tuesday, how many megawatts can this specific substation safely import?), and you rarely get a physical answer. You get an administrative lookup from an annual or seasonal study.

Power 2026 showed what happens when a transmission line hits its limit: congestion binds and nodal prices split. Part 1 examines what sets that limit in the first place, why the published rating diverges from physical capability almost every hour of the year, and how that gap shapes every auction and tariff that follows.

Lattice transmission towers crossing a prairie, conductors highlighted in red
A line rated for the worst hour of the year, carrying power through the other 8,759.
Chapter 01

The node question

Walk up to a bulk substation and ask the utility how much power it can import right now. You will get a static or seasonal rating printed in a planning table. Historically, engineers calculated that limit under simultaneous worst-case weather assumptions: a 40°C (104°F) afternoon, full solar irradiance, and nearly dead air, roughly 0.6 m/s (2 ft/s) of wind. Their job was to ensure the overhead aluminum-steel conductor would never overheat, anneal, or sag into trees during the ugliest afternoon of the summer.

Physically, an overhead transmission line is an uninsulated resistor cooled by the wind. Current flowing through resistance generates heat proportional to I2 R. As the conductor warms, the metal expands and the span sags between towers; sag past the statutory ground or vegetation clearance, and you trigger a flashover fault, or a wildfire. On a brisk, 12°C October evening with a 5 m/s crosswind, convective cooling carries heat away rapidly, allowing that exact same wire to move far more current safely than it can in stagnant August heat.

For decades, North American grid operations ignored hourly weather and ran on seasonal static tables. In December 2021, FERC issued Order 881, instructing transmission owners to compute hourly ambient-adjusted ratings (AARs) incorporating forecast air temperature and solar heating.1 While the initial July 2025 compliance date saw extensions into 2028 for major regions including NYISO and MISO, the operational scale is massive: in MISO alone, compliance covers more than 13,000 transmission facilities and requires computing roughly 22 million forecasted hourly ratings.1 Federal regulation formally acknowledged that thermal capacity behaves like a weather forecast rather than a nameplate stamp.

Ambient temperature is still an indirect proxy because wind speed dominates conductor cooling. Clamp sensors onto the span (or monitor conductor tension and clearance directly) and you get dynamic line ratings (DLR). Department of Energy field demonstrations with NYPA and Oncor found up to 25% additional usable capacity over static ratings in most operating hours (and 30% to 70% over static averages in DOE's 2019 report to Congress).2 An empirical CIGRE analysis measured DLR averaging 33.8% more capacity than static ratings in summer and 19.3% more in winter.3 In the UK, National Grid deployed dynamic ratings across hundreds of circuit-kilometers, logging an average 8% circuit uplift and £21 million in avoided constraint payments.4

Fig. 1Same wire, more room
+0%+10%+20%+30%+40%AAR · summer+15.1%AAR · winter+2.7%DLR · summer+33.8%DLR · winter+19.3%National Grid DLR+8%
Average capacity uplift above static ratings for ambient-adjusted (15.1% summer / 2.7% winter) and dynamic line ratings (33.8% summer / 19.3% winter). Source: CIGRE US National Committee; National Grid UK.

Planners, however, care about the tail risk buried in the CIGRE dataset: during roughly 22% of summer hours, when wind speeds drop near zero in stagnant heat, real-time DLR actually dips below ambient-adjusted or static ratings.3 Extra wire capacity is abundant across 8,500 hours of the year, yet vulnerable during the exact stagnant heatwave hours that define resource adequacy. That catch explains why dynamic wire ratings work best when paired with fast, dispatchable load or storage on the receiving bus.

A stranded conductor with a red clamp-on line sensor
A dynamic line rating sensor clamps onto the conductor and reports temperature, sag, and tension.

Thermal sag is also only one item on the checklist. Query the same substation across different hours and four other physical limits take turns binding:

  • Voltage. Moving power across inductive lines causes voltage drop; heavy midday rooftop solar export pushes voltage up. On medium-voltage distribution circuits and weak transmission pockets, high or low voltage limits (0.95 to 1.05 p.u.) frequently cap power transfer long before conductors approach their thermal limit.
  • Stability. Synchronous generators across an interconnection spin in phase lock at 60 Hz. Pushing heavy power across long, high-impedance corridors widens the rotor angle separation between sending and receiving buses; stretch that angle too far and the system loses synchronism or suffers voltage collapse.
  • Protection. Breakers and relays must safely interrupt worst-case short-circuit fault currents. A transformer bank thermally capable of carrying 500 MW may be capped lower if parallel paths raise available fault current above downstream switchgear interrupting ratings.
  • Contingency (N−1). Bulk grid operators never load the network to its intact physical limit. Under mandatory NERC standards, the system must survive the sudden, unscheduled loss of any single major element, such as the largest generator or a critical transmission circuit (N−1), without cascading thermal overloads or voltage collapse. Holding back N−1 headroom keeps the lights on, while sidelining a substantial fraction of installed wire capacity every hour of the year.

Ask what a node can import right now, and the rigorous answer is a multivariable time series governed by wind speed, ambient heat, local reactive support, breaker ratings, and N−1 topology. Treating that living physical boundary as a single annual number leaves vast capability stranded in the wires.

Chapter 02

Nameplate vs. deliverable vs. available

Every large power transformer carries a stamped steel plate, and on a typical bulk bank it reads 500 MVA. In developer slide decks, that routinely gets transcribed as "500 MW of substation capacity." In reality, every piece of electrical infrastructure has three distinct capacity figures, and conflating them wrecks project timelines.

A large power transformer painted red, with three bushings and radiator fins
Nameplate: what the stamped steel plate says under ideal test conditions. Downstream reality is smaller.

Nameplate is the continuous rating stamped by the manufacturer under standardized cooling and ambient test conditions.

Deliverable is the maximum real power that can move through the surrounding network to load during stressed conditions without violating any thermal, voltage, stability, or N−1 limit from Chapter 1. Put a 500 MVA transformer downstream of a congested 300 MW transmission corridor, and you have a 300 MW substation. Interconnection studies obsess over deliverability because generation trapped behind a transmission bottleneck during peak hours contributes zero reliability to the load pocket on the other side.

Available is the net deliverable headroom remaining this hour, after subtracting existing customer load, loop flows, scheduled maintenance outages, ambient derates, and operating reserves. Control room operators live on available capacity; prospective load customers almost never see it.

Three physical mechanisms eat away at nameplate capacity on its way to becoming available real power:

  • Reactive power (Q). Alternating-current networks require reactive power, measured in megavars (MVAR), to sustain the electromagnetic fields that hold up bus voltage. Transformers, lines, and inverters are thermally limited by total apparent power (S, in MVA), so the power triangle (S2 = P2 + Q2) caps real power at P = √S2 − Q2. At modest reactive loading (say, 100 MVAR on a 500 MVA bank), real power capability (P) dips slightly to √5002 − 1002 ≈ 490 MW. When heavy transfers across long inductive lines starve a load pocket of reactive support and push reactive demand to 300 MVAR, real transfer plunges nonlinearly to 400 MW. Two identical circuits can carry markedly different real-power payloads depending on whether local capacitor banks, STATCOMs, or smart inverters are supporting local voltage.
  • Resistive losses (I2 R). Because line losses scale with the square of current, doubling power flow across a congested corridor quadruples resistive heating losses. Delivering 100 MW to a stressed urban load pocket can require 106 MW or 108 MW of upstream injection during peak hours. Marginal losses consume generation and wire capability right when both are scarcest.
  • Stability margins. On long transfer paths into major load centers, transient angular stability or post-contingency voltage collapse frequently caps safe imports 15% to 30% below conductor thermal limits. Those caps never appear on public utility maps, yet they govern operations inside the Energy Management System (EMS).

Errors between administrative ratings and physical availability cut in two directions:

Phantom capacity exists in market ledgers (accredited, cleared, and paid) yet fails to materialize during physical stress. Winter Storm Elliott in December 2022 exposed gigawatts of accredited PJM gas and coal units that tripped or failed to start due to frozen instrumentation and gas-supply pressure drops. (ERCOT's February 2021 Winter Storm Uri failure occurred outside a formal capacity market, driven by unweatherized thermal plants and fuel-grid interdependence, while CAISO's August 2020 rotating outages stemmed primarily from net-peak planning gaps and tight regional imports.)

Hidden capacity is the mirror image: physical transfer capability, storage, and flexible load that exist on the network right now, capable of serving or relieving a node, yet uncounted because planners lack real-time telemetry and granular market mechanisms to verify it. Virtually all regulatory reform over the past decade has focused on eliminating phantom capacity. Unlocking hidden capacity remains wide open.

Chapter 03

Hosting capacity is a time series

Most utility SCADA systems stop having clear vision right at the distribution substation feeder breaker. Downstream of that breaker, medium-voltage feeders (4 kV to 34.5 kV) snake down streets to serve neighborhoods, strip malls, cold-storage warehouses, and commercial buildings. Planners historically designed radial distribution circuits for one-way power flow, substation to meter, sized for hot late-afternoon air-conditioning peaks and left largely unmonitored in between.

A suburban street of solar-roofed houses with the distribution line running pole to pole in red
A distribution feeder: at 1:00 PM its rooftops push power backward; at 7:00 PM EVs and heat pumps pull hard from the substation.

Widespread rooftop solar, behind-the-meter batteries, and EV fast chargers broke radial assumptions. At 1:00 PM on a clear April afternoon, net power on a solar-heavy feeder flows backward toward the substation, lifting voltage along the circuit and confusing legacy directional relays. Six hours later, the sun drops, EVs plug in, commercial HVAC stays running, and the exact same wire flips to heavy import. A feeder's hosting capacity (how much additional injection or load it can absorb without violating thermal, steady-state voltage, rapid voltage change, or protection limits) shifts every hour across all three phases.

California is currently the only jurisdiction forcing investor-owned utilities to model and operationalize those hourly curves publicly. Under CPUC Rule 21, PG&E, SCE, and SDG&E publish an Integration Capacity Analysis (ICA): per-node feeder limits calculated across 288 representative monthly-hourly profiles (24 hours × 12 months).5,6 In March 2024, California regulators took the logical next step by authorizing Limited Generation Profiles (LGPs).7 Rather than failing interconnection screens, and triggering multi-million-dollar transformer or reconductoring upgrades, because a circuit is full at 1:00 PM in May, a solar-plus-storage developer can interconnect using a certified, time-varying export schedule capped within 90% of the modeled hourly ICA envelope (replacing an archaic "15% of peak load" rule of thumb).7,8 Hardware certification under UL 3141 slowed initial rollouts through 2025, yet the regulatory precedent is unmistakable: static worst-hour screens strand physical grid capacity, while scheduled envelopes unlock it.

Transmission engineers often point out a crucial voltage distinction here: a 150 MW AI training campus connects at bulk subtransmission or transmission voltage (69 kV, 115 kV, 138 kV, or 230 kV), never on a 12.47 kV neighborhood feeder that maxes out around 10 MW to 15 MW. Why, then, does distribution-edge hosting capacity govern the data center crunch?

For two concrete physical reasons:

  1. Upstream substation and transmission relief. Every megawatt pulled by distribution feeders flows straight through the bulk step-down transformers and regional transmission interfaces feeding that load pocket. When 40,000 homes and 200 commercial buildings downstream of a constrained 230/69 kV substation curtail or battery-shift 80 MW during the 40 hottest early-evening hours of the summer, they directly free 80 MW of bulk N−1 import headroom on the high-voltage bus where the hyperscale data center wants to connect.
  2. Modular edge and regional inference clusters. Latency-sensitive inference nodes and modular 5 MW to 25 MW compute deployments increasingly target existing industrial parcels fed at subtransmission or primary distribution voltages (13.8 kV to 34.5 kV). At those voltages, static utility hosting-capacity PDFs routinely label circuits "zero capacity available" based on a handful of peak hours, hiding 8,700 hours of usable import capability.

Across both voltage tiers, planning against the single worst hour of the year leaves vast off-peak and controllable-peak capability dark.

Chapter 04

From physics to product

No regional operator can finance thirty-year power plants solely through phone calls and five-minute spot dispatch. Over the past three decades, regulators and ISOs constructed an administrative layer called resource adequacy (RA) to translate the hourly nodal physics of Chapters 1 through 3 into standardized compliance products.

The translation pipeline follows a standard sequence. Planners adopt a probabilistic reliability target, traditionally a loss-of-load expectation (LOLE) of "one day in ten years" (0.1 event-days/year). Monte Carlo simulations of weather, load, and generator outages convert that target into a system Planning Reserve Margin: say, 15% to 20% above forecasted coincident peak demand. Load-serving entities receive a slice of that requirement proportional to their customers' peak load, and satisfy it by owning plants, signing bilateral contracts, or paying an ISO auction to procure standardized capacity credits (typically denominated in MW-day or kW-month).

Fig. 2The lossy compression
Nodal physicseach bus, each hour− locationReliability target0.1 LOLE− timeReserve margin~18% over peak− performanceCapacity creditzonal, seasonal UCAPinformation kept
Hourly nodal physics → 0.1 LOLE reliability target → ~ 18% planning reserve margin → Zonal annual/seasonal UCAP credit. The strip above each box is a schematic, not a measurement.

Power 2026 demonstrated how marginal energy pricing captures physical congestion every five minutes. Capacity markets borrow marginal-clearing auctions while stripping out the physical resolution that makes nodal energy markets honest:

  • Spatial compression. Power flow is nodal; capacity zones span multiple states or vast utility footprints. Until a coarse Locational Deliverability Area (LDA) boundary binds, a megawatt of capacity credit 200 miles away clears identically to a megawatt right inside a congested substation pocket.
  • Temporal compression. Grid stress concentrates in narrow seasonal weather windows: August heat domes at 6:00 PM, January polar-vortex mornings at 7:00 AM. Traditional capacity obligations clear as flat annual or seasonal blocks, forcing complex statistical patches whenever wind, solar, or four-hour batteries enter the stack.
  • Performance lag. Administrative accreditation relies on historical outage averages or simulated fleet models rather than real-time physical telemetry. PJM introduced its Capacity Performance penalties after the January 2014 Polar Vortex exposed high forced-outage rates, then had to overhaul accreditation again after Winter Storm Elliott in December 2022 caught gas units failing to deliver during extreme cold.

Seen clearly, America faces two distinct capacity challenges requiring different toolkits:

  1. The steel deficit: insufficient transformers, high-voltage lines, and firm generation in fast-growing load pockets. Solving this demands capital, permitting reform, supply-chain expansion, and decade-scale construction.
  2. The observability deficit: gigawatts of existing wire thermal headroom, behind-the-meter storage, and curtailable commercial/compute load that physically sit on constrained paths today, yet cannot be seen, trusted, dispatched, or settled by grid operators.

Part 2 examines the five administrative machines the United States built to manage resource adequacy, and how data center load growth is pushing each of them to its design limit.

Part 2 / 4

How capacity is managed across the United States

America operates three physical interconnections (Eastern, Western, and Texas), governed by a patchwork of regional transmission organizations, state public utility commissions, and vertically integrated monopolies. Across that footprint, five distinct administrative regimes attempt to guarantee enough deliverable power shows up during peak stress.

A desert substation yard with one bank of breakers highlighted in red
One interconnected physical machine per region; five different administrative rulebooks layered on top.
Chapter 05

The map

The U.S. power map offers five different institutional answers to how far ahead capacity should be bought, who draws the demand curve, and whether capacity should be a separate product at all.

Fig. 3Five regimes, one grid
U.S. capacity regimes by grid operator footprintMap of the contiguous United States colored by resource adequacy regime: PJM in the Mid-Atlantic and Ohio Valley runs a multi-year forward auction; NYISO, MISO across the Midwest and South-Central states, and ISO-NE run prompt or seasonal auctions; ERCOT covers most of Texas with energy-only pricing; CAISO in California uses mandatory bilateral resource adequacy; the rest of the West relies on bilateral contracting and utility planning; the Southeast and SPP rely on vertically integrated utility planning.PJMMISOSPPERCOTCAISONYISOISO-NESoutheastWest
  • Multi-year forward auction · PJM
  • Prompt / seasonal auctions · NYISO, MISO, ISO-NE
  • Energy-only scarcity pricing · ERCOT
  • Mandatory bilateral RA · CAISO and California
  • Western bilateral and utility planning · Rest of the West
  • Vertically integrated IRPs · Southeast and SPP
The contiguous United States colored by how each grid operator's footprint buys capacity, using the five archetypes listed at the end of this chapter. ISO-NE is grouped with the prompt auctions it moves to in 2028; the rest of the West, mostly outside organized capacity markets, is shown in a lighter shade of the bilateral color. Boundaries are balancing-authority areas, which approximate market footprints; Alaska and Hawaii are not shown. Source: balancing-authority boundaries from Electricity Maps (derived from EIA data); state lines from the U.S. Census Bureau via us-atlas.

PJM runs the world's largest mandatory forward capacity market, serving roughly 67 million people across 13 Mid-Atlantic and Midwestern states plus D.C. Its Reliability Pricing Model (RPM) uses a Base Residual Auction (BRA) designed to clear three years ahead of the delivery year, procuring unforced capacity (UCAP) against an administratively sloped demand curve.9 Load-serving entities must participate unless they opt out entire load zones under the Fixed Resource Requirement (FRR) self-supply alternative. Following multi-year rule litigation that compressed its auction calendar, PJM ran back-to-back auctions in 2024, 2025, and July 2026, aiming to restore full three-year-forward spacing by May 2027.9

ISO New England operated a parallel three-year Forward Capacity Market (FCM) for nearly two decades; its eighteenth auction (FCA 18, for 2027/2028) cleared 31,556 MW at $3.58/kW-month across all zones.10 Then New England pulled the plug on the three-year horizon. Concluding that procuring capacity 36 months ahead created severe load-forecast and queue-attrition risk, ISO-NE filed its Capacity Auction Reforms, winning FERC approval for Phase 1 on March 30, 2026 (Docket ER26-925) to transition to a prompt auction held roughly one month before delivery starting in 2028, with seasonal commitment periods and accreditation updates following in Phase 2.10

NYISO already runs prompt, granular capacity auctions: six-month seasonal strip auctions, monthly auctions, and binding monthly spot auctions backed by steep locational demand curves. Because transmission into downstate New York is tightly constrained, New York City (Zone J) and Long Island (Zone K) clear on dedicated local curves. For Summer 2025, NYC's ICAP demand curve carried a reference price of $17.37/kW-month and a maximum clearing cap of $41.30/kW-month; actual Q3 2025 spot clearing averaged $15.84/kW-month in NYC versus $5.80/kW-month in Rest-of-State: nearly a threefold spread driven purely by physical import limits into the five boroughs.11

MISO, stretching across 15 states from Minnesota and Manitoba down to Louisiana, operates a seasonal Planning Resource Auction (PRA) each spring covering Summer, Fall, Winter, and Spring slices. Historically a vertical-demand residual market where vertically integrated utilities self-supplied and traded leftovers at near-zero prices, MISO introduced a sloped Reliability-Based Demand Curve for 2025/2026: summer prices jumped 22-fold to $666.50/MW-day (later partially resettled in August 2025 after MISO uncovered a modeling bug in the curve, a move its independent market monitor sharply criticized).12 By April 2026 (the 2026/2027 PRA), summer prices moderated to $384–$424/MW-day as accredited solar supply jumped 59% year-over-year to 12.2 GW.12

ERCOT rejects capacity markets altogether. Texas runs an energy-only design where generators recover fixed capital costs through real-time energy and ancillary-service scarcity spikes. From June 2014 through late 2025, ERCOT relied on its Operating Reserve Demand Curve (ORDC) to inject administrative scarcity adders up to $5,000/MWh as operating reserves thinned. On December 5, 2025, ERCOT launched Real-Time Co-Optimization plus Batteries (RTC+B), retiring the ORDC in favor of explicit Ancillary Service Demand Curves that co-optimize energy and reserves every five minutes.13

CAISO and the Western Interconnection rely on mandatory bilateral Resource Adequacy. California's 38 load-serving entities sign bilateral RA contracts for System, Local, and Flexible capacity and submit monthly and annual compliance filings to the CPUC and CAISO. After raising its legacy monthly peak reserve margin to 17% in 2024, California implemented its Slice-of-Day framework full-time in 2025: utilities must now prove they hold enough deliverable generation and storage-charging energy across all 24 individual hours of each month's worst peak day.14 Slice-of-Day is America's most explicit regulatory attempt to align resource adequacy with hourly time-series physics.

The Southeast and much of SPP remain predominantly vertically integrated outside retail-choice capacity auctions. Monopolies like Southern Company, Duke Energy, and TVA forecast load in state-supervised Integrated Resource Plans (IRPs), run all-source RFPs, and recover approved plant investments directly through regulated rate base. (Even here, rapid data center arrivals forced new hybrid mechanisms, such as SPP's Conditional High Impact Large Load service approved by FERC in 2026.25)

Sorting those seven footprints yields five structural archetypes:

  1. Multi-year forward auctions (PJM): lock in prices years ahead against planner load forecasts.
  2. Prompt and seasonal auctions (NYISO, MISO, and post-2028 ISO-NE): clear close to the delivery season with lower forecast error.
  3. Energy-only scarcity pricing (ERCOT): fold reliability incentives entirely into real-time energy and reserve prices.
  4. Mandatory bilateral showings (CAISO / Western RA): require hourly/monthly bilateral contracting verified by regulators.
  5. Regulated IRP rate-basing (Southeast / parts of West & Midwest): substitute utility commission prudence reviews for wholesale clearing prices.
Chapter 06

Anatomy of a capacity auction

In July 2026, PJM released the clearing results for its 2028/2029 Base Residual Auction. Every modeled zone across the thirteen-state footprint cleared at the maximum legal price cap of $325.00/MW-day of unforced capacity, procuring 138,317.8 MW in the auction while still finishing 6,831.3 MW UCAP short of PJM's reliability requirement (a 14.7% reserve margin against a ~ 20% target).15 Only 524.7 MW UCAP, just 0.38% of cleared supply, came from new generation and uprates.15 Understanding how the country's premier capacity machine hit the ceiling three auctions in a row while barely attracting new steel requires opening the hood on RPM.

An empty grid control room with a curved desk facing a blank red video wall
Inside the ISO: transmission flows are tracked every few seconds, while capacity auctions clear years ahead on spreadsheet forecasts.

On the demand side sits PJM's Variable Resource Requirement (VRR) curve, an administratively drawn downward-sloping line anchored around Net CONE: the estimated net annual revenue a hypothetical new reference combustion turbine or combined-cycle plant needs beyond energy-market margins to break even. When offered supply falls below the target reliability requirement, the VRR curve climbs toward a price cap; when supply exceeds the target, clearing prices slide sharply downward.

On the supply side, existing capacity resources face a must-offer obligation designed to prevent physical withholding, paired with market-power mitigation caps tied to avoidable going-forward costs. Where aggregate supply crosses the VRR curve sets a uniform clearing price paid to every cleared MW-day. Whenever transmission import limits into a constrained sub-region, a Locational Deliverability Area (LDA), prevent cheaper upstream supply from serving local load, that LDA separates and clears at a higher local price. In the July 2024 auction (for 2025/2026), while RTO-wide PJM jumped nearly tenfold from $28.92 to $269.92/MW-day, constrained pockets in Baltimore Gas & Electric ($466.35/MW-day) and Dominion Virginia ($444.26/MW-day) hit their local price caps first.16

Clearing an auction carries strict physical liability under PJM's Capacity Performance rules. Whenever PJM declares emergency Performance Assessment Intervals (PAIs) during system reserve shortages, every committed resource is measured against its expected share of delivery. Underperformers pay steep non-performance charges that fund bonus payments to overperforming generators. Originally pegged to Net CONE after the 2014 Polar Vortex, penalty stop-loss limits triggered multibillion-dollar disputes after Winter Storm Elliott in 2022, prompting FERC to approve rebasing a resource's annual stop-loss cap to 1.5 × its own BRA clearing revenue.17 (PJM's Independent Market Monitor, Monitoring Analytics, has repeatedly criticized both the administrative penalty rate and narrowed PAI triggers that now make actual assessment intervals rare.17)

Look at the five-auction trajectory across PJM:

  • 2024/2025 BRA: $28.92/MW-day RTO-wide, pricing abundance and accelerating coal and older gas retirements.16
  • 2025/2026 BRA (held July 2024): $269.92/MW-day RTO-wide ($444–$466 in constrained LDAs), driven by generator retirements, stricter ELCC accreditation, and surging data center load forecasts.16
  • 2026/2027 BRA (held July 2025): Pinned at the newly negotiated FERC price cap of $329.17/MW-day across the entire footprint.16
  • 2027/2028 BRA (held Dec 2025): Pinned at the $333.44/MW-day cap ($121,705/MW-year), securing 134,479 MW in the BRA plus 11,299 MW in FRR plans (~ 145,777 MW total after decimal rounding), falling roughly 6,516 to 6,623 MW UCAP short of the reliability target (14.8% reserve margin).15,18 PJM simulated that without the cap, prices would have cleared 60% higher at ~ $193,907/MW-year.18
  • 2028/2029 BRA (held July 2026): Pinned at the extended $325.00/MW-day cap across all zones, 6,831.3 MW UCAP short (14.7% reserve margin), representing ~ $16.4 billion in annual capacity procurement with uncapped simulated prices topping $202,000/MW-year.15
Fig. 4PJM RTO capacity clearing prices ($/MW-day UCAP)
$0$100$200$300$400$292024/25$2702025/26held Jul 2024$3292026/27held Jul 2025 · cap$3332027/28held Dec 2025 · cap$3252028/29held Jul 2026 · cap
2024/25 ($28.92) → 2025/26 ($269.92) → 2026/27 ($329.17, capped) → 2027/28 ($333.44, capped) → 2028/29 ($325.00, capped). Source: PJM Interconnection.

Why did record prices attract almost zero net-new power plants in 2028/2029? Because gas turbine supply chains, permitting, and interconnection queues take five to seven years, whereas a compressed forward auction clears two years ahead against utility load forecasts swollen by data center requests. Forward auctions price planner anxiety years before new steel can physically respond.

Chapter 07

Accreditation, or what counts

Before any megawatt enters a capacity auction, the grid operator decides what fraction of its nameplate actually counts toward reliability. That conversion math, called accreditation, shifts billions of dollars between asset classes every time an ISO updates its weather risk model.

Historically, thermal plants used simple availability math: PJM translated Installed Capacity (ICAP) into Unforced Capacity (UCAP) via the plant's historical Equivalent Demand Forced Outage Rate:

UCAP = ICAP × (1 − EFORd)

Under that regime, a 500 MW gas turbine with a 5% historical forced outage rate sold 475 MW of UCAP, silently assuming mechanical failures were statistically independent across generators. Winter Storm Elliott shattered that assumption when extreme cold knocked out dozens of gas and coal units simultaneously.

Starting with the 2025/2026 delivery year (accepted by FERC in January 2024), PJM transitioned nearly its entire fleet (renewables, storage, demand response, and thermal classes alike) onto marginal Effective Load Carrying Capability (ELCC).19 Marginal ELCC runs thousands of hourly weather and outage simulations to ask: if we add one more megawatt of this resource class to the projected fleet, how much "perfect" 24/7 lossless capacity can we remove while keeping system loss-of-load risk constant?

Because marginal ELCC measures contribution during the exact hours when reserves run dry, ratings shift dynamically as fleet penetration and seasonal risk evolve. Compare PJM's published ELCC class ratings across the 2025/2026, 2027/2028, and 2028/2029 Base Residual Auctions:19

Resource Class 2025/26 BRA 2027/28 BRA 2028/29 BRA Physical Driver
Nuclear 95% 95% 96% High winter/summer firmness; rare uncorrelated outages
Gas Combined Cycle 79% 74% 78% Winter gas supply / freeze correlation derates
Gas Combustion Turbine 62% 61% 67% Starting reliability & non-firm pipeline exposure
4-Hour Battery Storage 55% 58% 59% Strong summer evening peak coverage; winter duration limits
10-Hour Battery Storage 77% 78% 78% Covers multi-hour winter morning/evening ramps
Onshore Wind 38% 41% 34% Stronger winter performance than solar
Tracking Solar 14% 8% 10% Zero output during winter evening / pre-dawn freeze peaks
Demand Resource (DR) 77% 92% 91% Jumped after FERC ER25-1525 made DR dispatchable 24/7

Fig. 5 PJM Marginal ELCC Class Ratings (share of nameplate counting as UCAP). Source: PJM ELCC Class Ratings reports (2025–2026).

Two numbers in that table deserve close inspection. First, tracking solar sits at 8% to 10%: adding another 100 MW solar array yields just 8 to 10 MW of accredited capacity because solar saturation has pushed PJM's loss-of-load hours into dark winter mornings and evenings. Second, look at Demand Resource: after dipping from 77% (2025/26) to 69% (2026/27) due to legacy rules that restricted curtailment calls to narrow daytime windows, stakeholders and PJM eliminated the performance window restriction under FERC Docket ER25-1525, making DR callable 24/7 year-round and updating winter load shapes.19 Demand response accreditation immediately jumped to 92% in 2027/28 (and 91% in 2028/29).19

Every accreditation battle across the country (PJM's marginal ELCC, ISO-NE's upcoming seasonal accreditation, CAISO's transition from ELCC to monthly hourly exceedance profiles) reflects the same underlying reality: administrative markets are slowly re-learning that capacity value depends entirely on which hours a resource can perform. Yet class-level annual averages remain a blunt instrument. A battery or flexible data center located directly inside a thermally constrained substation bus gets the exact same class ELCC percentage as one sitting behind unconstrained wire two states over.

Chapter 08

The bilateral world

Public ISO capacity auctions capture almost all the industry commentary because their clearing prices print in press releases. Across the United States as a whole, however, most capacity never touches a public auction. It changes hands through private bilateral contracts and state-regulated utility balance sheets.

In vertically integrated territories across the Southeast, Pacific Northwest, and Mountain West, state utility commissions oversee Integrated Resource Plans. Utilities project ten- to twenty-year demand, secure regulatory approval for new natural gas, solar, and storage portfolios, and run competitive Requests for Proposals (RFPs). Developers bid confidential prices; the utility selects winners and builds rate-base assets; ratepayers fund guaranteed return on equity. Tens of gigawatts of generation get financed without a single public clearing price ever posting.

A modernist stone utility headquarters with a single red door
Across vertically integrated states, state regulatory commissions and bilateral RFPs replace public capacity auctions.

Even inside organized wholesale markets, bilateral deals carry most of the load:

  • MISO's seasonal auction clears only the thin residual margin left after vertically integrated utilities self-supply or contract bilaterally.
  • PJM's Fixed Resource Requirement (FRR) lets major utilities pull entire load footprints out of the BRA using bilateral and owned portfolios.
  • California's Resource Adequacy market runs entirely on bilateral "RA-only" contracts, often traded month-ahead or year-ahead at confidential prices, which obligate the seller to submit must-offer bids into CAISO's day-ahead and real-time energy markets.

Commercial power desks trade capacity through specialized structures that complement the spark spreads and heat-rate call options covered in Power 2026:

  • Tolling agreements: The buyer pays a fixed monthly $/kW-month capacity payment to take operational dispatch control of a gas plant or battery, supplying fuel (or charging energy) and keeping all wholesale market revenues. Battery tolls have become the dominant financing structure in ERCOT and California.
  • Shaped capacity strips: Bilateral blocks covering peak summer (July–August) or winter (January–February) months rather than full calendar years.
  • 24/7 Carbon-Free Energy (CFE) agreements: Pioneered by Google in 2020, hourly clean-energy matching requires procuring deliverable firm clean resources (nuclear, geothermal, hydro, or multi-hour storage) capable of generating in the exact hours within the same regional grid when wind and solar drop off.

For a data center developer, bilateral opacity creates an immediate blind spot. Published industrial retail tariffs reflect embedded historical average costs of plants built twenty years ago, hiding the steep marginal cost of adding 100 MW to a maxed-out load pocket today. Only after filing a formal load interconnection request does the buyer discover the real physical price tag.

Part 3 / 4

How data centers procure capacity

Parts 1 and 2 laid out the physical limits of the wires and the five market rulebooks layered over them. Part 3 follows a hyperscale or AI infrastructure developer trying to energize 100 MW at a specific parcel on an eighteen-month schedule, and colliding head-on with utility planning timelines built for five-year industrial cycles.

A long data hall of dark server racks, one row painted red
A hundred megawatts from the inside: densely metered, software-controlled, and arriving faster than transmission upgrades can be permitted.
Chapter 09

The load request

Energizing a large data center campus begins with a formal large-load interconnection application to the local transmission or distribution owner, specifying target megawatts, ramp schedule, power factor, and load-drop sensitivity.

Utility transmission planners then run a System Impact Study: the node question from Chapter 1 executed in reverse. Power-flow and transient-stability models inject the proposed 100 MW draw onto the local 115 kV or 230 kV bus across peak summer, peak winter, and light-load shoulder cases, tripping each nearby line and transformer one by one (N−1) to check for thermal overloads or voltage collapse. If an upstream 345/138 kV autotransformer overloads under contingency, the project gets handed a Facilities Study quote for a new bank or reconductored corridor, plus a three- to six-year wait for high-voltage equipment and siting permits.

For a century, utilities socialized bulk network upgrades across all ratepayers on the safe assumption that new factories and housing subdivisions grew steady regional tax and kWh bases over forty years. AI data centers shattered that regulatory compact when developers began submitting overlapping 200 MW to 1,000 MW applications across five utilities simultaneously while shopping for the fastest site.

Central Ohio became the national proving ground. Facing more than 30,000 MW of data center interconnection requests around Columbus, against an existing central Ohio data center load of ~ 600 MW in 2024 and an entire AEP Ohio system peak of 8,000 to 10,500 MW, AEP Ohio froze new agreements and petitioned the Public Utilities Commission of Ohio (PUCO) for a dedicated data center tariff.20 Approved on July 9, 2025 (Case 24-508-EL-ATA), the tariff applies to new data centers above 25 MW and enforces strict financial commitments: an 85% minimum monthly billing demand (take-or-pay whether compute racks are installed or not), a four-year ramp cap, contract terms up to twelve years (eight years post-ramp), steep exit fees, and upfront liquid collateral.20

What happened next proved that utilities were starving for certainty even more than electrons. On February 12, 2026, AEP Ohio reported back to PUCO after enforcing the new collateral and 85% take-or-pay window: the 30,000+ MW queue distilled down to 5,642 MW of signed binding contracts.20 Over 80% of the paper queue evaporated the moment applicants had to put balance-sheet capital behind their load forecasts.

Fig. 6Central Ohio data center capacity
0 MW10,000 MW20,000 MW30,000 MWOperating load, 2024~600 MWQueue before tariff30,000+ MWBinding contracts, Feb 20265,642 MW
2024 operating load (~ 600 MW) vs. pre-tariff queue (>30,000 MW) vs. binding post-tariff contracts signed by Feb 2026 (5,642 MW). Source: AEP Ohio PUCO filings.

Across the country, regulators and ISOs spent 2025 and 2026 codifying two parallel tracks for large loads, pay-for-certainty tariffs and conditional/expedited interconnection:

  • Over 60 state large-load tariffs have been approved or filed across Georgia (100 MW+ minimum-bill rules), Indiana, Virginia, Arizona, and beyond.21
  • Texas SB 6 (enacted June 2025) mandated standardized financial commitments, disclosure of duplicate site requests, remote curtailment capability during emergencies, and 120-day ERCOT reliability reviews for net-metering/co-location deals above 75 MW, paired with ERCOT's 2026 "Batch Zero" study reforms.21,22
  • PJM's Critical Issue Fast Path (January 2026 Board directive) established an expedited Bring Your Own New Generation (BYOG) study track for large loads pairing dedicated new supply, alongside a Reliability Backstop Procurement design.21,23
  • SPP's Conditional High Impact Large Load (CHILL) service, accepted by FERC effective July 1, 2026 (195 FERC 61,196), explicitly lets large loads connect ahead of long-lead transmission upgrades if they accept automated temporary curtailment during system contingencies.25
Chapter 10

Finding capacity

Five years ago, data center site selectors ranked parcels on fiber latency to Ashburn or Santa Clara, industrial land prices, water rights, and state sales-tax exemptions on servers, treating utility power as an item ordered twelve months before ribbon-cutting. Today, time to power overrides nearly every other line item on the pro forma. Site selection has become nodal capacity discovery run in reverse.

A graded empty parcel bounded by red construction fencing, beside a substation
Site selection in 2026: hunting for graded industrial acreage adjacent to a substation with unallocated N−1 transformer and line margin.

Sophisticated infrastructure teams now employ former ISO transmission planners to reconstruct utility load-flow models (PSS®E or PowerWorld) before signing land options. They scrape OASIS transmission-service tables, state IRP filings, transformer bank ratings, and regional expansion plans to estimate how many megawatts a given 138 kV or 230 kV bus can absorb before triggering a major network upgrade. They also cross-reference upstream generator interconnection queues, knowing that a retiring coal plant or an energizing 400 MW battery bank directly alters post-contingency flows across the target bus.

Generator queues illustrate why waiting on traditional grid expansion breaks AI hardware cycles. According to Lawrence Berkeley National Laboratory's Queued Up tracking, roughly 2,600 GW of generation and storage (more than twice the entire existing U.S. fleet) sat in interconnection queues at the end of 2023, with completed projects taking nearly five years from initial request to commercial operation.24 FERC Order 2023 (issued July 2023 and upheld unanimously by the D.C. Circuit in Advanced Energy United v. FERC in July 2026) replaced serial first-come, first-served bottlenecks with first-ready, first-served cluster studies and financial withdrawal penalties.24 Even with cluster reform, permitting high-voltage lines and procuring large power transformers, whose manufacturing lead times stretch 30 to 48 months, keeps physical wire expansion on a half-decade clock.

Meanwhile, utility engineering departments face a compounding study crunch: the exact same 15 transmission planners running Order 2023 generator cluster studies are simultaneously drowning in 50 MW to 500 MW data center load studies.

Because outside California almost no utility publishes hourly nodal import headroom across subtransmission and distribution substations, site markets clear on asymmetric private knowledge. A brownfield industrial site sitting next to a 115 kV ring bus with 85 MW of genuine N−1 headroom commands an immense valuation premium over an identical parcel five miles away behind a thermally maxed corridor, yet public maps rarely distinguish the two.

Chapter 11

The commercial menu

Once an interconnection path is secured, a data center operator chooses how to contract for energy and capacity. Each rung up the commercial menu attempts to bypass another layer of administrative delay or price risk from Part 2:

  1. Regulated utility tariff service. The buyer signs a large-load ESA under state-approved industrial or data-center tariffs (such as AEP Ohio's or Georgia Power's), letting the monopoly utility handle all generation and transmission planning. Execution is straightforward, though the customer absorbs embedded utility cost escalations and multi-year construction queues.
  2. Competitive retail choice. Available in roughly fourteen deregulated states (including Texas, Ohio, Pennsylvania, and Illinois), retail suppliers unbundle commodity energy pricing from local utility wire charges. Capacity obligations still pass through from the underlying ISO (e.g., PJM BRA charges or ERCOT ancillary costs), which sophisticated buyers hedge via fixed-capacity retail blocks or pass-through caps.
  3. Direct wholesale market participation. Large campuses can register directly as wholesale market participants (or work with a licensed scheduling coordinator), settling nodal LMP energy and managing PJM FRR or bilateral capacity positions directly. That path is increasingly attractive when PJM auctions clear at $325–$333/MW-day caps.
  4. Virtual and sleeved PPAs. Corporate sustainability standards popularized long-term contracts with wind and solar farms, either settled financially as contracts-for-differences (virtual PPAs) or physically scheduled ("sleeved") through a retail provider. Standard annual-volumetric PPAs hedge energy prices and supply renewable energy certificates (RECs), while leaving local nodal peak capacity entirely up to the host grid.
  5. 24/7 hourly carbon-free matching. Contracting clean resources hour-by-hour within the same regional grid forces buyers to underwrite storage, geothermal, hydro, or nuclear capacity that delivers during dark, windless hours, aligning corporate procurement much closer to physical resource adequacy.
  6. Dedicated nuclear restarts. In September 2024, Microsoft signed a 20-year PPA with Constellation Energy to restart the retired 835 MW Three Mile Island Unit 1 reactor in Pennsylvania (renamed the Crane Clean Energy Center), backed by a $1 billion DOE loan guarantee closed in November 2025 and targeting an accelerated 2027 return to service.26 With a 95%–96% PJM ELCC rating, restarting an existing nuclear site brings massive firm capacity onto an existing high-voltage switchyard without building greenfield transmission.
A nuclear cooling tower beside a long data-center building, the switchyard between them in red
Connecting near generator terminals: high firm capacity, fierce regulatory scrutiny over grid cost-shifting.
  1. Generator co-location. Connecting a data center directly behind the meter of an operating power plant promised an enticing shortcut around transmission queues, until regulators stepped in. When Talen Energy sought to expand Amazon Web Services' co-located load agreement at Pennsylvania's 2,494 MW Susquehanna nuclear plant from 300 MW to 480 MW (toward a planned 960 MW campus), FERC rejected the amended Interconnection Service Agreement in November 2024 (rehearing denied April 2025), citing transmission cost-shifting and grid reliability risks.27 What followed reshaped the entire sector: * Talen and AWS restructured their partnership in mid-2025 into a massive $18 billion, 17-year, 1,920 MW front-of-the-meter PPA, agreeing to take full wholesale transmission delivery rather than bypassing the grid.27 * On December 18, 2025, FERC issued a landmark order directing PJM to establish formal transmission-service categories and cost-allocation rules for all co-located loads (followed by FERC's June 18, 2026 orders across six regional ISOs).21,27 * Having pivoted to front-of-the-meter service, Talen voluntarily dismissed its federal court appeal (Susquehanna Nuclear v. FERC, transferred from the Fifth Circuit to the Third Circuit, No. 25-3167) in January 2026.27 Pure behind-the-meter "free riding" on grid-connected baseload plants is effectively over.
  2. Onsite behind-the-meter generation ("islanded or bridge microgrids"). Facing four-year utility substation delays, several AI developers are installing banks of reciprocating natural gas engines, aeroderivative gas turbines, solid-oxide fuel cells, and BESS directly on campus, operating either completely islanded from the grid or as multi-year "bridge power" until utility transmission arrives.
A row of containerized gas turbines with red exhaust stacks
Onsite gas turbines and fuel cells cost more per MWh and complicate emissions targets, yet buy immediate time to power.

Every step down that list reflects buyers paying an escalating premium to reclaim what static grid planning failed to deliver: guaranteed megawatts at a known bus on an AI-relevant calendar.

Chapter 12

Flexible load as capacity

Ask an AI infrastructure VP whether their 100 MW cluster can curtail load to help the grid, and their reflexive answer is usually "absolutely not; our GPUs cost too much to sit idle." Run the actual hardware amortization math, and you quickly see both why naive demand-response pitches fail and why surgical, sub-50-hour flexibility is one of the highest-return trades in power markets.

Start with the silicon ledger. A 100 MW AI data center houses roughly 50,000 frontier accelerators representing $2.5 billion to $3.5 billion in server and networking capital. Depreciated over a four-year economic life (~ 35,000 hours), carrying that hardware costs $70,000 to $100,000 per hour, equivalent to $700 to $1,000 per MWh of curtailed power before counting lost revenue or synchronous pre-training checkpoint overhead. Any utility program asking a hyperscaler to power down racks for 500 hours a year is dead on arrival.

Now run the interconnection ledger. Sitting in a transmission upgrade queue waiting three years for a new 230 kV line costs 26,280 consecutive hours of delayed deployment, or forces the developer to spend $150M+ building a full-scale onsite gas power plant. Meanwhile, as Chapter 1 and Duke University's widely cited Rethinking Load Growth analysis demonstrated, bulk grid capacity bottlenecks bind during a tiny sliver of the year: typically the 20 to 50 sharpest weather-stress hours (less than 0.5% of the 8,760 hours in a year).28

Suppose a 100 MW campus commits 30 MW of verified, ten-minute dispatchable load relief during those 30 peak hours a year, delivered through a combination of:

  • Workload orchestration: throttling asynchronous post-training, reinforcement-learning rollouts, batch offline inference, or shifting latency-tolerant API traffic geographically across campuses;
  • Thermal cooling pre-chilling and UPS/BESS buffering: riding four-hour onsite lithium-iron-phosphate batteries or EPA-compliant Tier 4 backup generators to shave net grid draw without dropping a single GPU clock cycle.

What does that 30 MW of surgical flexibility earn?

  1. Years faster time-to-power: Under conditional interconnection frameworks like SPP's CHILL tariff, PG&E's Flex Connect, or ERCOT's curtailable load structures, capping net draw during N−1 peak hours lets the facility energize 24 to 36 months ahead of bulk transmission upgrades. Trading <10 full-cluster hours of annual workload throttling to gain 20,000+ hours of early cluster operation is an overwhelming net-present-value win.
  2. Direct capacity revenue: Under PJM's updated 24/7 Demand Resource rules (91%–92% ELCC) at the 2028/2029 clearing price of $325.00/MW-day, 30 MW of registered curtailable load (30 MW × 0.91 × $325 × 365) generates $3.24 million per year in capacity payments, offsetting onsite battery CapEx while directly alleviating the regional reserve shortfall.15,19 In ERCOT, Emergency Response Service (ERS) and ancillary markets pay stand-ready availability fees, while avoiding Four Coincident Peak (4CP) transmission intervals saves millions more in annual wire charges.29 California's Base Interruptible Program (BIP) and Demand Side Grid Support (DSGS) similarly pay monthly $/kW incentives for rapid peak drops.29

Yet even these existing programs remain blunt side doors: PJM's BRA prices flexibility zonally years ahead, while utility interruptible tariffs use rigid static baselines and ignore local distribution relief. Neither mechanism lets a constrained substation dynamically buy 30 MW of net import relief from both the data center and thousands of surrounding batteries and commercial buildings on the exact same bus.

Part 4 / 4

Transactive capacity

Parts 1 through 3 traced a structural mismatch: grid physics operates nodally and hourly, administrative capacity markets clear zonally and multi-annually, and 100 MW compute loads are building private gas plants because the gap between the two takes five years to navigate. Part 4 lays out the missing market layer needed to close that gap, and walks through the exact engineering and financial math of a single substation unlock.

A small white house with a red solar array on its roof beside a large tree
Forty-seven gigawatts of behind-the-meter flexible hardware already sits installed across North America, most of it invisible to nodal capacity planning.
Chapter 13

From static product to dynamic capacity

Every capacity construct surveyed in Part 2 treats capacity as a static credential. You clear a megawatt of UCAP for a twelve-month or three-month strip years or months ahead, and the credential carries identical weight on a mild Tuesday in May and a 39°C Thursday in August. Settlement turns on administrative availability checks and rare emergency penalty intervals rather than continuous metered delivery.

If you designed a capacity product directly around the physics of Part 1, its specification would look completely different:

  • Nodal or substation-specific: scoped to the exact transformer bank or transmission interface where thermal, voltage, or N−1 limits bind.
  • Time-specific: procured for the actual four-hour peak window tomorrow (or seasonal peak block) when forecasted load approaches real-time dynamic equipment limits.
  • Technology-neutral across voltage tiers: indifferent to whether 20 MW of net bus relief comes from a utility-scale battery at 69 kV, a data center throttling batch training jobs, or 4,000 residential batteries and commercial rooftop HVAC units discharging downstream on 13.8 kV feeders.
  • Telemetry-settled: paid on verified, revenue-grade sub-hourly meter data with symmetrical financial non-performance penalties.

Call this transactive capacity: firm, locational, time-specific net deliverability, priced dynamically against real physical constraints and settled on measured performance.

Wholesale energy markets already proved that five-minute nodal optimization works across tens of thousands of buses; that is the Locational Marginal Pricing (LMP) engine Power 2026 detailed (settled every five minutes in most ISOs, and every fifteen minutes in ERCOT real-time). Ancillary service markets already procure sub-hourly spinning and regulation reserves. What hasn't existed is a market mechanism connecting nodal wire and transformer headroom to dispatchable behind-the-meter and large-load flexibility so new loads can interconnect immediately without waiting five years for worst-hour steel upgrades.

Veteran market designers raise two fair objections whenever dynamic capacity comes up:

  1. Project finance requires multi-year certainty: Nobody borrows $800 million for a combined-cycle plant or nuclear restart against volatile day-ahead nodal capacity prices.
  2. Regulators require forward reserve visibility: Governors and utility commissions want proof three years ahead that winter peak load is covered.

Transactive capacity layers cleanly on top of forward financing rather than abolishing it, just as wholesale power pairs 15-year bilateral PPAs and forward hedges with five-minute nodal spot dispatch. Long-term forward contracts and tariffs underwrite baseload steel and bulk transmission backbones; dynamic nodal capacity clears the sharp 1% of peak hours at constrained substations, allowing utilities to connect 100 MW loads years faster while deferring or right-sizing capital upgrades.

Chapter 14

The edge as supplier

You do not have to wait five years for gas-turbine supply chains to manufacture the flexible supply side of a transactive capacity market. Millions of controllable assets already sit bolted to garage walls, commercial rooftops, and industrial electrical rooms across North America.

An open garage with an electric SUV charging and a red home battery on the wall
Already financed, permitted, and wired: residential batteries, EVs, and smart HVAC represent tens of gigawatts of latent substation relief.

According to Wood Mackenzie's November 2026 North America Virtual Power Plant report, behind-the-meter flexible VPP capacity expanded 25.9% year-over-year to reach 47.2 GW (up from 37.5 GW in 2025).30 Residential share of wholesale-market VPP capacity jumped 155% year-over-year, driven by retailer-led home battery programs and opt-out enrollments, while storage and EV participation grew nearly 20% relative to legacy thermostat programs.30 Most tellingly for this primer, Wood Mackenzie's 2026 scorecard documented a brand-new market segment that didn't exist twelve months earlier: VPP providers disclosed a 1 GW pipeline of aggregated edge capacity built specifically to unlock and offset data center load in constrained regions led by PJM and ERCOT.30 Looking toward 2030, the Department of Energy's Pathways to Commercial Liftoff report estimates scaling U.S. VPPs to 80–160 GW could displace peaker buildouts and save roughly $10 billion annually in grid infrastructure costs,31 while major residential aggregators (including a June 2026 Sunrun, Tesla, and Renew Home framework targeting 16.8 GW of residential flexibility) are assembling utility-scale portfolios.32

Fig. 7North American VPP capacity trajectory
0102030405033.0 GW202437.5 GW2025+13.7%47.2 GW2026+25.9%
33.0 GW (2024) → 37.5 GW (2025, +13.7%) → 47.2 GW (2026, +25.9%), with 1 GW now directly targeting data center load pockets. Source: Wood Mackenzie (Nov 2025 & Nov 2026 reports).

Yet look closely at what is still stuck behind regulatory friction. Even as aggregate VPP capacity reached 47.2 GW, Wood Mackenzie noted that economic wholesale market participation contracted 13.5% year-over-year, and vast swaths of newly installed residential and commercial batteries remain unmonetized due to utility meter-data barriers and opt-in friction.30

At the federal level, FERC issued Order 2222 back in September 2020 to open wholesale energy, ancillary, and capacity markets to distributed energy resource (DER) aggregations down to 100 kW.33 Six years later, the institutional plumbing remains half-built:

  • PJM's full Order 2222 energy and market implementation has slipped to February 2028/2029; when DER aggregations became eligible on paper ahead of PJM's July 2026 (2028/2029) Base Residual Auction, zero MW of Order 2222 aggregations cleared.15,33
  • NYISO targeted late-2026 implementation, handicapped by a 10 kW individual-asset minimum capability rule that shuts out most residential batteries and EV chargers.33
  • Across all organized markets tracked by Pacific Northwest National Laboratory in early 2026, not a single state had completed end-to-end operational coordination protocols between wholesale aggregators and local distribution utilities.33

Hardware isn't the bottleneck anymore; institutional visibility, telemetry, and settlement infrastructure are.

Chapter 15

The four hard problems

Why have dozens of "transactive grid" utility pilots over the past decade ended in glossy whitepapers without changing how substations are planned? Because four coupled engineering and institutional problems stand between a fleet of smart devices and a capacity product a transmission planner will bet their license on.

Fig. 8The transactive capacity stack
Accreditationplanners credit it in impact studiesSettlementrevenue-grade telemetry, not baselinesDispatchdeterministic, with DSO overrideVisibilitysub-minute nodal telemetry
Sub-minute Nodal Visibility → Deterministic Dispatch & DSO Override → Revenue-Grade Telemetry Settlement → Regulatory Accreditation. Each layer depends on the one beneath it.
  1. Sub-minute nodal visibility. Standard residential and commercial "smart meters" (AMI) were built for monthly billing, typically backhauling 15-minute or 60-minute kWh intervals over mesh networks once every 6 to 24 hours. A distribution operator managing an overloaded 138/13.8 kV substation transformer at 5:45 PM cannot wait until tomorrow morning to find out what happened on Phase B of Feeder 4. True transactive capacity requires real-time edge telemetry: knowing right now which batteries hold state-of-charge, how much curtailable load sits online behind specific phase conductors, and where local voltage and thermal margins stand.
  2. Deterministic dispatch and TSO-DSO override. Sending cloud API requests to 10,000 heterogeneous inverters, chillers, and EV chargers introduces packet drops, firmware quirks, and human opt-outs. Worse, uncoordinated wholesale dispatch can break local wires: if high wholesale energy prices trigger 500 batteries on a single radial feeder to discharge simultaneously, or snap back into synchronized "rebound charging" at 9:01 PM, they can blow a pole-top transformer fuse or trip feeder overcurrent relays. A production system requires closed-loop control with an unambiguous safety hierarchy: automated market dispatch by default, paired with low-latency local utility (DSO) operating envelopes capable of capping exports or imports on specific feeders within seconds, while immediately notifying the wholesale schedule to rebalance.
  3. Gaming-proof settlement. Generators and front-of-the-meter batteries have dedicated revenue meters; demand reduction measures a counterfactual: what load would have drawn absent dispatch. Administrative Customer Baseline Load (CBL) formulas invite moral hazard (artificially inflating pre-event consumption to get paid for phantom drops) and break down completely for spiky AI training or EV-charging profiles. Transactive capacity requires shifting wherever possible from counterfactual baselines to firm capacity envelopes and direct sub-metered asset verification: contracting a campus or feeder aggregation to stay strictly below a hard, metered MW import ceiling (say, ≤ 70 MW net at the point of interconnection) or verifying direct inverter kW injection at revenue-grade accuracy (ANSI C12.20).
  4. Accreditation and planning integration. Even flawless software stalls if utility transmission and distribution planners still treat flexible edge resources as zero-credit load reductions in System Impact Studies. Scaling beyond one-off pilots requires structuring performance guarantees, collateral, and automated hardware fail-safes strong enough that utility engineers and state regulators formally credit nodal transactive capacity as a non-wires bridge or permanent alternative to multi-year steel upgrades.

None of the incumbent silos naturally owns all four layers: utilities stop at the meter, ISOs stop at the transmission substation, device OEMs only see their own walled garden, and hyperscalers just want energized racks. Building the unified layer across all four is missing market infrastructure.

Case study

Unlocking 60 MW at Oakridge Substation

To see how all four layers fit together in practice, and why the unit economics work for every party at the table, walk through a concrete substation transaction in a constrained PJM load pocket (modeled on typical 230/69 kV delivery points in Virginia and central Ohio).

The Physical Bottleneck

Consider Oakridge Substation, a bulk step-down yard fed by a double-circuit 230 kV transmission line. Two parallel 230/69 kV autotransformers (Bank 1 and Bank 2), each stamped 150 MVA top-stage nameplate (ONAN/ONAF2), feed a 69 kV subtransmission ring. That 69 kV ring serves local industrial customers alongside three downstream 69/13.8 kV distribution substations (14 radial feeders supplying 28,000 homes, 180 commercial rooftops, and two refrigerated logistics warehouses).

Under IEEE C57.91 thermal loading criteria, if Bank 1 trips offline during a 38°C summer afternoon (N−1), Bank 2 can safely carry a four-hour emergency load of 172 MVA without exceeding winding hot-spot insulation limits. At the bus's summer peak power factor (cos φ = 0.96, carrying ~ 48.2 MVAR of reactive demand), the firm real-power N−1 import limit on the 69 kV bus is:

Pmax, N−1 = Semerg × cos φ = 172 MVA × 0.96 = 165.1 MW ≈ 165 MW

Existing coincident load across the 14 downstream feeders peaks at 140 MW at 6:00 PM on the hottest August weekday. Subtracting 140 MW from the 165 MW N−1 ceiling leaves exactly 25 MW of static firm available capacity.

Now an AI infrastructure operator files a large-load request to connect a 60 MW training and inference campus (~ 30,000 frontier GPUs; $1.8 billion in IT capital) directly to the Oakridge 69 kV ring.

  • Static System Impact Study verdict: Adding 60 MW pushes peak bus demand to 200 MW, creating a 35 MW N−1 thermal overload (21% above Bank 2's emergency rating).
  • Traditional steel cure: Install a third 150 MVA 230/69 kV autotransformer, expand the 230 kV breaker-and-a-half bay, and reconductor 4.2 miles of 69 kV subtransmission tie-line. Estimated cost: $28.5 million. Estimated energization timeline: 42 months (driven by a 34-month large power transformer manufacturing slot plus outage scheduling).
  • Onsite gas alternative: Deploying 35 MW of behind-the-meter aeroderivative gas turbines requires $52 million in CapEx, ~ $115/MWh in delivered fuel and maintenance costs, and an 18-to-24-month air-permitting fight in a county near NOx ozone non-attainment limits.

The 8,760-Hour Time-Series Reality

Pull the actual hourly SCADA load history for Oakridge Substation across a full weather-normalized year and overlay the proposed 60 MW data center draw (Ltotal(t) = Lexisting(t) + 60 MW):

  • Combined bus load crosses the 165 MW N−1 limit (meaning existing feeder load exceeds 105 MW) during only 34 hours per year, concentrated across nine July/August heatwave afternoons (4:30 PM to 8:30 PM) and two January polar-vortex mornings (6:30 AM to 8:30 AM).
  • Across the other 8,726 hours of the year (99.6% of all hours), Oakridge Substation already has enough physical N−1 transformer capability to serve the entire 60 MW campus with zero thermal violation.
  • Total cumulative overload energy above 165 MW across all 34 hours is just 620 MWh (an average deficit of 18.2 MW during constrained hours, peaking at 35 MW in the single worst hour of August).
Fig. 9Thirty-four hours strand the other 8,726

Sorted annual load across all 8,760 hours (left) vs. the top 55 peak hours (right). Static N−1 planning stalls 60 MW of compute for 42 months over a 620 MWh sliver.

A. Full-year load duration curveHours 1–8,760 · scale 0–220 MW
A. Full-year load duration curveAll 8,760 hours sorted from highest to lowest bus load. Existing feeders run from 140 MW down to 46 MW; adding the 60 MW campus lifts the combined curve above the 165 MW N-1 limit only in the first 34 hours. The rest of the year sits below the limit.05010014016520002,0004,3806,5008,760hHours of the year (sorted highest to lowest load)Substation real power (MW)34-hour N−1 overload (0.39%)200 MW peak (+35 MW) · see panel B165 MW N−1 firm limit (172 MVA × 0.96)8,726 hours of spare N−1 headroom99.6% of the year stays below 165 MW+60 MW AI campus loadSteady, high-duty-cycle computeExisting 14 distribution feeders (13.8 kV)140 MW peak · 66 MW median · 46 MW minimum
B. Zoomed peak window and transactive dispatchHours 1–55 · zoomed scale 100–210 MW
B. Zoomed peak window and transactive dispatchThe 55 most stressed hours. Combined load starts at 200 MW and falls to the 165 MW limit at hour 34. The wedge above the limit, 620 MWh a year, is covered by campus flexibility for its lower part and edge DERs for the top 20 MW, holding net flow at or below 165 MW.1001201401651802000102034h4555hTop 55 stressed hours of the year200 MW peak (+35 MW)Layer 1: Edge DERs (20 MW)2,400 home BESS · 12 C&I · HVAC/EVLayer 2: Campus flex (18 MW)10 MW LFP BESS + 8 MW batch flexNet dispatched flow ≤ 165 MW620 MWh / yrTotal wedge energy(0 h past hour 34)Existing 14 feeders140 MW (hour 1) → 105 MW (hour 34)
34 h / yrBinding N−1 window (0.39% of the year)
620 MWhAnnual energy dispatched (0.14% of campus load)
38 MW firm20 MW edge DERs + 18 MW campus flex
$1.89M / yr netBridge cost ($4.23/MWh) vs. a 42-month queue wait
Illustrative PJM 230/69 kV substation load-duration profile (2 × 150 MVA autotransformers; IEEE C57.91 four-hour emergency N−1 rating of 172 MVA, or 165 MW at 0.96 power factor), with the 60 MW AI campus added: a 35 MW peak deficit binds across just 34 hours a year (620 MWh in total), leaving 99.6% of hours unconstrained.

Assembling the 38 MW Transactive Stack

Instead of waiting 42 months for Bank 3 before energizing racks, the utility, the data center developer, and a transactive capacity operator structure a 36-month bridge interconnection (energizing in Month 8 once the customer's 69 kV tap switchyard is built, while Bank 3 proceeds on its normal construction schedule). To give utility planners an 8.6% deterministic reserve buffer above the 35 MW peak deficit, the market procures 38 MW of firm, four-hour nodal relief electrically downstream of Oakridge's 230/69 kV transformers across two layers:

Nodal Resource Slice Voltage Bus Enrolled Nameplate Firm 4-Hr Accredited Relief Dispatch Mechanism
2,400 Residential BESS (13.5 kWh / 5 kW; 32.4 MWh fleet) 13.8 kV (14 feeders) 12.0 MW 7.5 MW Direct inverter discharge into evening peak
12 C&I BESS + Cold-Storage Thermal 13.8 kV (Feeders 2, 5, 9) 8.5 MW 7.5 MW Sub-metered battery export + warehouse compressor ride-through
4,200 Smart HVAC & Depot EV Chargers 13.8 kV (14 feeders) 7.2 MW 5.0 MW Staggered duty-cycle curtailment with post-9 PM ramp-rate limit
Data Center Onsite LFP BESS (40 MWh) 69 kV campus bus 10.0 MW 10.0 MW Discharges behind campus POI breaker during peak windows
Data Center Workload Orchestration 69 kV campus bus 12.0 MW 8.0 MW Pauses async RL/post-training queues + pre-chills thermal loop
Total Oakridge Nodal Portfolio Oakridge 69 kV 49.7 MW 38.0 MW Holds net 230/69 kV flow ≤ 162 MW (3 MW below N−1 limit)

Solving the Four Hard Problems at Oakridge

How does a conservative utility protection engineer sign off on energizing 60 MW against distributed batteries and software? By enforcing all four layers from Chapter 15 in hardware:

  • Visibility: Every C&I battery, residential inverter gateway, and campus breaker streams 2-second telemetry (active power P, reactive power Q, voltage V, and usable kWh state-of-charge) into a nodal state estimator integrated with the utility's ADMS, paired with real-time top-oil temperature sensors on Oakridge Banks 1 and 2.
  • Deterministic Dispatch & DSO Override: Whenever day-ahead weather forecasts push projected Oakridge bus demand above 150 MW, enrolled batteries receive automated pre-charge schedules by 2:00 PM. During the 4:30 PM–8:30 PM window, closed-loop dispatch tracks Oakridge high-side flow every 15 seconds. Local DSO dynamic operating envelopes cap discharge on solar-heavy Feeder 7 if local primary voltage reaches 1.045 p.u., shifting the dispatch call seamlessly to C&I units on Feeder 2.
  • Physical Fail-Safe Backstop (ANSI Protection): Utility engineers never rely on cloud APIs alone to protect a $10 million autotransformer. As a condition of early energization, the data center wires a utility-controlled direct transfer trip / automated load-runback scheme at its 69 kV point-of-interconnection relay. If Bank 1 actually suffers an unscheduled fault (N−1 contingency becomes N-0 reality) and downstream edge resources ever under-deliver such that Bank 2 current exceeds 172 MVA for more than 90 seconds, local protection hardware automatically throttles the data center's non-critical feeder breakers down to its firm 25 MW static allocation. The transformer is 100% physically protected in milliseconds.
  • Gaming-Proof Settlement: Neither the data center nor the battery fleet settles on gameable counterfactual baselines. During called Oakridge peak intervals, the data center settles on a hard metered import ceiling (≤ 42.0 MW net at its revenue-grade 69 kV meter, backed by $25/kW liquidated-damages penalties). Residential and C&I batteries settle directly on ANSI C12.20 inverter kW output meters; only the 5.0 MW HVAC slice uses randomized weather-matched control groups.

The Cash-Flow Ledger

Compare the three-year bridge economics across all three counterparties:

For the Data Center Buyer (34 months faster energization)
  • Gross Nodal Cost: Pays a bilateral nodal capacity reservation fee of $180/kW-year (~ $493/MW-day) for the 20 MW of community edge relief ($3.60M/year), plus $1.95M/year in annualized financing on its $13M onsite 10 MW / 40 MWh LFP battery = $5.55 million/year gross cost.
  • Wholesale Market Revenue Offset: Registers its 18 MW campus flexibility (10 MW 4-hour BESS at 59% ELCC + 8 MW 24/7 DR at 91% ELCC = 13.18 MW UCAP) into PJM's wholesale market at $325/MW-day ($1.56M/year), captures PJM 5-Coincident-Peak (5CP) transmission tag avoidance across 18 MW (~ $1.45M/year), and earns ~ $0.65M/year in LMP energy arbitrage and synchronized reserves.
  • Net Cost & NPV Impact: Net out-of-pocket bridge cost drops to $1.89 million/year, equivalent to just $4.23/MWh spread across the campus's 60 MW load (85% load factor). In exchange for <$2M/year and ~ 272 MWh/year (about 4.5 full-cluster hours, or 0.05% of the year) of paused batch jobs, the operator brings $1.8 billion of GPUs online 34 months early, capturing 24,800 hours of frontier AI compute revenue while avoiding $52M in stranded gas turbines.
For Edge Asset Owners & Aggregator

The $3.60M/year nodal pool (plus stacked PJM wholesale DR/energy revenues) pays participating homeowners $675 to $750/year per 13.5 kWh home battery and pays cold-storage warehouses $140/kW-year, roughly double to triple standard utility demand-response payouts, driving rapid local opt-in enrollment across Oakridge's 14 feeders while leaving 20%–25% platform margin to fund edge telemetry hardware and SLA collateral.

For the Host Utility & Existing Ratepayers

The utility collects full 60 MW subtransmission delivery tariff revenues nearly three years ahead of schedule, spreading fixed grid costs across 446,000 MWh/year of new billing determinants to put downward pressure on residential rates, while retaining hardwired relay protection on Bank 2 and gaining full real-time visibility across 14 distribution feeders before Bank 3 ever energizes.

Chapter 16

The thesis

Put the sixteen chapters together on one page:

  1. Capacity is a nodal, hourly physical boundary. How many megawatts a substation can import or export this hour depends on wind cooling, conductor sag, reactive power (S2 = P2 + Q2), voltage stability, and N−1 contingency topology. Static ratings set for the single hottest, calmest afternoon of the year leave substantial physical capability unused across the other 8,759 hours.
  2. Every U.S. capacity regime is a lossy compression of that boundary. Forward auctions in PJM, seasonal and prompt auctions in MISO, NYISO, and ISO-NE, energy-only scarcity adders in ERCOT, bilateral Slice-of-Day showings in California, and state-regulated IRPs in the Southeast all trade away spatial and hourly precision to create manageable administrative products.
  3. AI compute growth is breaking the static planning clock. When 100 MW loads arrive in eighteen months against five-year transformer and transmission lead times, forward auctions pin at $325–$333/MW-day caps without summoning fast new steel, utilities impose 85% take-or-pay filters to flush out speculative queues, and developers resort to expensive onsite gas turbines to buy certainty.
  4. Forty-seven gigawatts of edge hardware and flexible compute already sit on the grid, waiting for the instrumentation to count. As Oakridge Substation shows, pairing surgical 30-to-40-hour data center flexibility with aggregated residential and commercial storage downstream of the exact same constrained transformers turns a three-and-a-half-year interconnection wait into an eight-month energization bridge at a net cost under $5/MWh.
The same suburban street at dusk, with a few windows glowing red
Same feeder at 8:00 PM: solar export has ended, garage batteries discharge into the local peak, and nodal headroom reopens.

Static capacity markets worked well enough when demand grew at 1% a year and every meaningful asset was a central-station steam or gas turbine wired to the bulk transmission network. They buckle when hundred-megawatt compute campuses collide with tens of gigawatts of unmonitored behind-the-meter hardware.

Power 2026 closed by observing that the answer to most electricity pricing questions is "it depends." For capacity, what it depends on is concrete: which bus, which hour, and whether anyone has built the telemetry, control, and settlement layer to prove what physically showed up. Something we dedicate ourselves to at Elastic Energy.

Quick answers

Capacity in seven questions

What is grid capacity, and how is it different from energy?

Energy is measured in megawatt-hours: how much electricity is consumed over time. Capacity is measured in megawatts: how much power the network can guarantee to deliver to a specific bus during the hours when the local grid is stressed. That limit is set hour by hour by thermal ratings, voltage, stability, protection and N−1 contingency margins, so it is a nodal, hourly quantity rather than a single annual number.

Why is grid capacity the bottleneck for AI data centers?

Large loads now ask for 100 MW or more on eighteen-month schedules, while large power transformers take 30 to 48 months to manufacture and roughly 2,600 GW of generation and storage sat in U.S. interconnection queues at the end of 2023. Static planning rules size every connection against the single worst hour of the year, so substations that have headroom for most of the year still report no capacity available.

How do U.S. capacity markets work?

The United States runs five resource adequacy regimes: multi-year forward auctions (PJM), prompt and seasonal auctions (NYISO, MISO and, from 2028, ISO-NE), energy-only scarcity pricing (ERCOT), mandatory bilateral resource adequacy (CAISO and much of the West), and vertically integrated utility planning (the Southeast and much of SPP). PJM’s last three Base Residual Auctions cleared at their price caps of $329.17, $333.44 and $325.00 per MW-day.

What is transactive capacity?

Transactive capacity is firm, locational, time-specific net deliverability, priced against real physical constraints and settled on measured performance. Instead of an annual zonal credit, a constrained substation buys relief for the specific hours it needs it, from batteries, flexible data center load or aggregated home and commercial devices on the same bus.

Can flexible data center load speed up grid interconnection?

Yes. Bulk grid constraints typically bind in only 20 to 50 hours a year, under 0.5% of the 8,760 hours. A campus that can cap its net draw in those hours, through workload orchestration and on-site batteries, can connect under conditional interconnection frameworks years ahead of transmission upgrades. Under PJM’s 24/7 demand response rules, 30 MW of dispatchable flexibility also earns about $3.24 million a year in capacity payments.

How did the Oakridge case study unlock 60 MW?

At the illustrative Oakridge 230/69 kV substation, adding a 60 MW AI campus overloads the 165 MW N−1 limit in only 34 hours a year, a 620 MWh wedge. A 38 MW portfolio of residential and commercial batteries, smart HVAC and EV chargers, and campus batteries and workload flexibility holds net flow at or below 165 MW. The campus energizes in month 8 instead of waiting 42 months for a new transformer, at a net bridge cost of about $1.89 million a year, or $4.23 per MWh.

How does capacity2026 relate to Power 2026?

capacity2026 is an independent, honorary sequel to Neel Somani’s Power 2026 (power2026.ai). Power 2026 explains how electricity gets its price, the megawatt-hour. capacity2026 covers the other number on the bill, the megawatt: how much power the grid can deliver to a specific node in the hours that matter.

Sources & primary citations

1FERC Order No. 881, Managing Transmission Line Ratings, 177 FERC 61,179 (Dec. 16, 2021), reh'g Order No. 881-A, 179 FERC 61,125 (2022). Original compliance deadline July 12, 2025; regional extensions granted into 2028 (including NYISO and MISO). MISO scope (~ 13,000+ facilities, ~ 22 million hourly forecasted ratings) documented via OATI compliance disclosures (PR Newswire). See also FERC Dynamic Line Ratings ANOPR, Docket No. RM24-6 (June 2024).

2U.S. Department of Energy, Dynamic Line Rating: Report to Congress (Aug. 2019), documenting NYPA (30%–44% over static) and Oncor (30%–70% over static averages) Smart Grid Demonstration results; industry summary in T&D World (tdworld.com).

3CIGRE U.S. National Committee, An Empirical Analysis of the Operational Efficiencies and Risks Associated with Line Rating Methodologies (2021): DLR averaged 33.8% above static in summer and 19.3% in winter; AAR averaged 15.1% and 2.7%, respectively, with DLR dipping below AAR during ~ 22% of low-wind summer hours (cigre-usnc.org).

4National Grid Electricity Transmission (UK) dynamic line rating deployment: average 8% circuit capacity uplift and £21M in avoided constraint costs across 2021–2026 (Electricity Forum).

5California Public Utilities Commission (CPUC) Rulemaking R.14-08-013 & Resolution E-5296 establishing Integration Capacity Analysis (ICA) 288 monthly-hourly nodal profiles (Solar Builder).

6Southern California Edison, Electric Rule 21: Generating Facility Interconnections: ICA thermal, steady-state voltage, power quality, protection, and operational flexibility calculations (sce.com).

7CPUC Limited Generation Profiles (LGP) decision (March 2024), authorizing smart-inverter export schedules bounded by hourly ICA hosting capacity (Solar Power World).

8CPUC Rule 21 Fast Track reform (June 2022), replacing legacy 15%-of-peak-load screen with 90%-of-ICA hourly screen (pv magazine USA).

9PJM Interconnection, Reliability Pricing Model (RPM) Manual 18 and 2025/2026 auction schedule updates targeting return to standard three-year-forward cadence by May 2027.

10ISO New England FCA 18 results (31,556 MW cleared at $3.58/kW-month for 2027/2028) and FERC Order accepting Phase 1 Capacity Auction Reforms transitioning to a prompt auction in 2028, Docket No. ER26-925 (March 30, 2026).

11NYISO Summer 2025 ICAP Demand Curve parameters (NYC reference price $17.37/kW-month, max clearing $41.30/kW-month) and Potomac Economics Q3 2025 NYISO Quarterly State of the Market Report ($15.84/kW-month NYC average spot vs. $5.80/kW-month Rest-of-State).

12MISO 2025/2026 Planning Resource Auction results ($666.50/MW-day initial summer clearing under the sloped Reliability-Based Demand Curve; resettled Aug. 2025) and April 2026 (2026/2027 PRA) results ($384–$424/MW-day summer clearing with 12.2 GW accredited solar, +59% YoY).

13ERCOT Real-Time Co-Optimization plus Batteries (RTC+B) go-live (Dec. 5, 2025), replacing the legacy Operating Reserve Demand Curve (ORDC) with Ancillary Service Demand Curves.

14CPUC Decisions D.22-06-050 and D.23-04-010 adopting the 24-hour Slice-of-Day Resource Adequacy framework (2024 test year; full binding compliance effective Jan. 1, 2025).

15PJM Interconnection, 2028/2029 Base Residual Auction Report (July 14, 2026): cleared 138,317.8 MW UCAP at the extended $325.00/MW-day price cap across all modeled LDAs, finishing 6,831.3 MW UCAP short of the reliability requirement (14.7% reserve margin; 524.7 MW UCAP new generation/uprates; ~ $16.4B total procurement; zero cleared Order 2222 DER aggregations).

16Congressional Research Service & PJM RPM historical results: 2024/2025 BRA ($28.92/MW-day RTO), 2025/2026 BRA ($269.92/MW-day RTO; $466.35 BGE; $444.26 Dominion), and 2026/2027 BRA ($329.17/MW-day RTO cap).

17FERC/NERC Joint Inquiry Report, Winter Storm Elliott (Nov. 2023); PJM Capacity Performance stop-loss reform rebasing annual non-performance cap to 1.5 × BRA clearing revenue; Monitoring Analytics, 2025 and Q1 2026 State of the Market Reports for PJM.

18PJM Interconnection, 2027/2028 Base Residual Auction Results (Dec. 17, 2025): cleared at $333.44/MW-day cap ($121,705/MW-year; simulated uncapped price $193,907/MW-year), procuring 134,479 MW UCAP in BRA plus 11,299 MW FRR (~ 145,777 MW published total), ~ 6,516–6,623 MW UCAP below reliability target (14.8% reserve margin).

19PJM Interconnection, ELCC Class Ratings for the 2025/2026, 2027/2028, and 2028/2029 Base Residual Auctions, and 2025 PJM ELCC and Reserve Requirement Study (Oct. 2025), documenting FERC Docket No. ER25-1525 removal of the Demand Resource availability window (lifting DR ELCC from 69% in 2026/27 to 92% in 2027/28 and 91% in 2028/29).

20Public Utilities Commission of Ohio (PUCO), Case No. 24-508-EL-ATA, Opinion and Order approving AEP Ohio Data Center Tariff settlement (July 9, 2025: >25 MW threshold, 85% minimum billing demand, up to 12-year commitment, collateral); AEP Ohio post-tariff PUCO status update (Feb. 12–13, 2026) reporting 5,642 MW of binding signed contracts following queue filtering (AEP Ohio News Release).

21State and ISO large-load proceedings: >60 state large-load tariffs filed/approved (Georgia Power 100 MW+ rule, I&M); FERC June 18, 2026 orders to six regional ISOs following DOE's large-load interconnection ANOPR.

22Texas Senate Bill 6 (enacted June 2025) & PUCT 2026 large-load interconnection and curtailment rules, including 120-day ERCOT co-location/net-metering impact reviews (>75 MW) and ERCOT Sept. 2026 Batch Zero framework.

23PJM Board of Managers Critical Issue Fast Path (CIFP) Large Load Additions decisional letter (Jan. 16, 2026) establishing the expedited Bring Your Own Generation (BYOG) study track and Reliability Backstop Procurement design (June 30, 2026 proposal).

24Lawrence Berkeley National Laboratory, Queued Up: 2024 Edition (~ 2,600 GW active interconnection queue at end of 2023; ~ 5-year median completion timeline); FERC Order No. 2023 (184 FERC 61,054, July 28, 2023), upheld in Advanced Energy United v. FERC, D.C. Cir. (July 31, 2026).

25Southwest Power Pool (SPP) High Impact Large Load (HILL), Docket No. ER26-247, 194 FERC 61,031 (Jan. 2026), and Conditional HILL (CHILL) curtailable rapid-interconnection service, 195 FERC 61,196 (effective July 1, 2026).

26Constellation Energy & Microsoft 20-year PPA (Sept. 2024) restarting the 835 MW Crane Clean Energy Center (formerly Three Mile Island Unit 1), targeting 2027 commercial operation following $1B DOE Loan Programs Office closing (Nov. 2025).

27FERC rejection of amended Susquehanna ISA, PJM Interconnection, L.L.C., 189 FERC 61,078 (Nov. 1, 2024), reh'g denied (April 2025); restructured June 2025 Talen–AWS $18B, 17-year, 1,920 MW front-of-the-meter PPA; FERC PJM Co-Location Order (Dec. 18, 2025, 195 FERC 61,209 compliance track); voluntary dismissal of Susquehanna Nuclear, LLC v. FERC, 3d Cir. No. 25-3167 (Jan. 2026).

28Tyler H. Norris et al., Nicholas Institute for Energy, Environment & Sustainability at Duke University, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems (2025), quantifying ~ 76–98 GW of U.S. load headroom achievable at 0.25%–0.5% annual curtailment hours.

29ERCOT Emergency Response Service (ERS, PUCT Subst. Rule §25.507, ercot.com); PG&E Electric Schedule E-BIP Base Interruptible Program (pge.com); California Energy Commission Demand Side Grid Support (DSGS, AB 205/AB 209, energy.ca.gov).

30Wood Mackenzie, North America Virtual Power Plant Market Report (Nov. 18, 2026): 47.2 GW behind-the-meter flexible capacity (+25.9% YoY from 37.5 GW in 2025), +155% YoY residential wholesale capacity expansion, and 1 GW disclosed VPP pipeline specifically targeting data center load (woodmac.com).

31U.S. Department of Energy, Pathways to Commercial Liftoff: Virtual Power Plants (2023; updated 2025): 80–160 GW 2030 target and ~ $10B/year avoided peaker and wire cost estimate.

32Sunrun, Tesla, and Renew Home announced residential aggregation framework targeting 16.8 GW of dispatchable home flexibility (June 2026).

33FERC Order No. 2222, 172 FERC 61,247 (Sept. 17, 2020); Pacific Northwest National Laboratory (PNNL), Order 2222 Implementation Tracking Report (Jan. 2026), documenting PJM Feb. 2028/2029 timeline, NYISO 10 kW minimum asset rule, and state DSO-aggregator coordination gaps.

About this primer

capacity2026.ai is a primer on data-center capacity procurement written by Ben Hilborn of Elastic Energy. It serves as an investor pre-read, a utility business-development guide, and an argument for transactive capacity: measuring, dispatching, and settling grid capacity nodally and hourly, the way the underlying physics actually works.

Written as an independent, unaffiliated sequel to Neel Somani's Power 2026. Any errors are mine.

Ben Hilborn · Elastic Energy · November 2026